07 · Logistics and installations

Multi-stage installations

One contract carried out on several dates and by different crews. We describe how to split an installation into stages, what each stage stores and how the contract status keeps up with them being closed.

Why split an installation

The customer ordered windows, doors and roller blinds, but it won't all go in at once: the windows arrive in March, the doors in April, the blinds only after the facade is done. Instead of three contracts, or one with a date pulled out of thin air, the contract gets three stages.

There are usually several reasons for splitting, and it is rarely about the office's convenience: goods arrive in batches, crews are busy, the customer asks for the work to be spread over time, or the installation depends on someone else's work — window sills, plastering, the facade.

What a stage stores

Number
The stage's order within the contract: 1, 2, 3.
Installation date
The day the stage is scheduled for.
Hours
Start and end, both optional. When filled in, they keep the crew's calendar in order when there are several addresses on one day.
Installer
A team member or a subcontractor. Each stage can have a different one — the windows installed by your own crew, the blinds by an external company.
Note
One sentence for the crew: “once the plaster has dried”, “entrance from the back yard, key with the neighbour”.
Completion marker
The date and time the stage was ticked off as done.

Example: three stages

  1. Stage 1 — windows, 12 March
    Your own crew, 8:00–14:00. After the installation you tick off the stage; the contract stays in progress, because two stages are still waiting.
  2. Stage 2 — doors, 9 April
    The same crew, note “RC3 front door, drop-down threshold seal”.
  3. Stage 3 — roller blinds, 20 May
    A subcontractor. Once this stage is ticked off, the contract moves to “Completed” on its own.

The contract status keeps up on its own

You don't need to change the status by hand — the system makes sure it matches what is happening on site:

Adding stages
A pending, ordered or ready contract moves to In progress. The installation date on the contract is set to the date of the earliest stage.
Ticking off one of several
Nothing changes. The contract stays in progress as long as at least one stage is waiting.
Ticking off the last one
The contract moves to Completed.
Unticking
If it turns out a stage wasn't finished after all, the contract goes back from “Completed” to In progress.
Deleting all stages
The contract goes back to Ready and returns to the queue of contracts to schedule.
Tick off after acceptance, not when the crew leaves
The contract status drives the dashboard and the summaries. A stage ticked off “in advance”, before the protocol is signed, inflates the number of completed contracts and pushes the job off the list of things to finish.

What this changes in your work

  • In the calendar the contract appears as many times as it has stages — each on its own day and with its own crew.
  • On the installation order a specific stage is printed, so the crew doesn't get a sheet listing work they aren't doing that day.
  • In the queue of contracts to schedule the contract disappears once the first stage is added — it doesn't come back to the list with each further one.

Planning stages in the crew calendar is described in Three views, and the printouts for the crew in PDF printouts.