How to calculate window installation cost without losing your margin

A lump sum for installation usually comes from comparing with the last job, not from adding up its parts. Here are seven costs that drop out of the quote and how to build your own crew day rate.

Alstre Team9 min read
How much does window installation really cost?

This is not a story about a badly priced job, but about a price worked out with the wrong method. A lump sum of "$3,500 for installation" usually comes from comparing with the last similar job, not from adding up what actually goes into it — so every deviation from the average quietly eats the margin. Below we break the cost of installation into its parts, show which of them most often drop out of the calculation, and build a rate you can apply to the next jobs instead of guessing every time.

Three costs that are almost always visible

Let's start with the ones nobody forgets, because every conversation about installation price begins with them.

Crew labour. Counted in crew working days, not in windows. The window is the unit you sell in, but not the unit in which the cost arises: a replacement in an occupied home takes two to three times longer than fitting the same windows on a building site, where there is nothing to protect.

Installation materials. Foam, fixings, vapour-permeable and vapour-tight tapes, silicone, adhesives, protective film. A small item per window, noticeable per job — and the first one to grow with three-layer sealed installation.

Transport. Delivering the windows to site, usually counted once. Why "once" is an optimistic assumption — more on that in a moment.

Seven costs that drop out of the calculation

This is the heart of it. Each of the items below is obvious once you think about it — and each regularly fails to make it into the quote, because it doesn't come up on a standard job.

  • Travel and travel time. Not just fuel, but the hours the crew didn't work. Two hours in the van there and back is a quarter of a working day for two people — on a job half an hour out of town that is a real loss, not a rounding error.

  • A second delivery. A missing item, a mixed-up sill, damage during unloading. Rare per window, frequent over a year — and practically never in the quote.

  • Removal and disposal. Carrying out the old windows, a skip or a trip to a waste site, the disposal fee. In an occupied building this can be half a day's work.

  • Reveal finishing. Making good after installation — included by some, charged separately by others, but it costs everyone. If the contract doesn't say plainly that it isn't included, the customer will assume it is.

  • Access at height. Scaffolding, a lift or a cherry picker. An item that can change the result of the whole job with a single line, and it only appears once you've seen the building.

  • Fixes and return visits. Adjustment after the season, re-sealing, replacing a scratched sash. Some of these are your obligation, some are goodwill — but all of them cost a crew day.

  • Downtime. The customer didn't let you in, the site wasn't ready, the delivery didn't arrive. The crew is paid regardless, and the day is lost.

The last four items have one thing in common: they cannot be assigned to a specific job at the time of quoting, because nobody knows yet whether they will happen. That is why they aren't priced per window but built into the rate — more on that below.

Price the crew day, not the window

Changing the unit of account does more here than any single fix to the price list. The window is the unit of sale, but cost arises over time: the same window takes a whole day or two hours depending on the building, the season and whether someone lives there.

Working out your own day rate takes an hour and goes like this. Take the annual cost of the crew — wages with employer on-costs, the van with fuel and servicing, tools and their wear, phones, workwear, training, insurance. Divide it by the number of days the crew actually worked at customers' sites, not by calendar days. That second part is the key and usually comes as a surprise: holidays, sick leave, bank holidays, downtime, days spent on fixes and weather typically eat between a fifth and a quarter of the year.

A rate calculated on calendar days is therefore twenty to twenty-five per cent too low — and that is the most common single reason why installation "somehow doesn't pay", even though each job on its own looked profitable.

A worked example

The figures below are examples meant to show the structure, not to set prices — plug in your own from your accounts.

Say a two-person crew costs $152,000 a year and works 190 days at customers' sites. The day rate comes to about $800 — and that is cost, not price. Add a share of the showroom's overheads, which installation doesn't get to carry for free either, plus your margin, and you arrive at the selling rate.

The job from the start of this article at that rate: four working days is $3,200 of crew cost, plus the second delivery, plus disposal, plus the return visit for adjustment — roughly the whole lump sum. Zero margin, on a quote that looked reasonable at first glance.

What to do with risk you can't predict

You can't price fixes, downtime and second deliveries on a specific job, because at the time of quoting nobody knows whether they will happen. But they are predictable over a year, and that is exactly how to treat them.

For one quarter, record three things against each job: how many crew days it actually took, how many extra trips there were and how many days went on fixes. After the quarter you know what share of the crew's time can't be assigned to any job — and that percentage is added to the day rate as a mark-up. For most showrooms it comes out between ten and twenty per cent.

It is the only honest way to have the easy jobs pay for the difficult ones, instead of subsidising them out of the margin on the windows.

What to put in the quote so you don't end up paying

Most of the losses on installation don't come from a rate that's too low, but from work done because "the crew was there anyway". One thing protects you: a written scope. The quote should state plainly what the price includes, and just as plainly what it doesn't.

  • removal of the old windows and who carries out the sashes,

  • taking away and disposal — with a price, if charged separately,

  • reveal finishing: what kind, on which side, to what standard,

  • internal window boards and external sills — fitting and making good beneath them,

  • access at height and who pays for it,

  • preparing the opening, if it turns out to be needed — the rate for that work,

  • the number of visits included in the price and the rate for each extra one,

  • work we will do on site for a fee, with a price list.

The last point is often skipped, yet it solves the most awkward situation in this job. The customer asks for a small favour, the installer doesn't know whether he's allowed to say no, does it for free, and it becomes a habit. A price list for small jobs takes the problem out of the installer's hands: it isn't a refusal, just a normal service for normal money. We write more about putting the quote itself together in the article on window quotes.

Seasonality to keep in mind when setting the rate

Window installation has a clear peak from late spring to autumn and a slump in winter. The consequence is simple and often overlooked: the crew's cost is fixed all year round, the revenue isn't. A rate calculated from the busy season looks great in July and doesn't cover February.

That is why working days are counted over the whole year, not over a good quarter. It is also an argument for cutting the price in winter deliberately and only down to a calculated floor — work below the full rate but above direct cost is better than standing idle. Provided you know where that floor is.

Where to get the data to work this out

The whole method above rests on one number: how many crew days a job really took. If installation dates live on a wall calendar and fixes are arranged by phone, that number simply doesn't exist and every calculation stays an estimate.

All you need is for three things to be recorded against each job: planned days, actual days and the reasons for the difference. After a quarter you have your own figures instead of someone else's examples. The installation calendar in the system keeps this record as part of scheduling, and the acceptance protocols show how many times the crew had to go back.

Disclaimer

This article describes a calculation method and industry practice. The figures in the example are illustrative and are not a price benchmark — crew costs, employment costs and company cost structures vary so much that the only reliable data is your own. Tax and accounting questions arising from how you book installation costs are worth settling with your company's accountant.